Work out the rate per unit of common building work, from earthwork and concrete to brickwork, plaster and paint. The quantities of materials, labour and machinery come from the CPWD Delhi Analysis of Rates 2023, and you can replace the basic rates with your own. Add items to build an estimate. Part of our quantity surveying tools.
How to use the rate analysis calculator
- Choose an item of work and enter the quantity.
- Open Basic rates and enter your city’s prices for cement, sand, aggregate, bricks, steel and labour.
- Set the water charges and the contractor’s profit and overheads. Tick GST and cess, or use Match CPWD DAR, to compare with the CPWD figure.
- Read the rate per unit and the full analysis, then tap Add to estimate.
- Repeat for other items, then download the estimate as CSV, print it or share a link.
Rate Analysis Calculator
Cost of one unit of common building work, from materials, labour and machinery, using the CPWD Delhi Analysis of Rates 2023
Basic rates (₹) — replace with your city's rates
Rate analysis
Estimate
Checks
Educational estimate. Quantities of materials, labour and machinery follow the CPWD Delhi Analysis of Rates 2023. Rates on your site depend on local prices, access, lead and job size. Not a quotation or a schedule of rates.
How the rate is built up
| Step | What is added |
|---|---|
| Materials, labour and machinery | Quantity of each resource for the unit × its basic rate, plus the fixed sundries, scaffolding and carriage amounts in the analysis. Their sum is W. |
| Water charges | 1% of W |
| GST (optional) | CPWD multiplying factor 0.2127 on the total so far |
| Contractor’s profit and overheads | 15% in the CPWD analysis; change it to suit |
| Labour cess (optional) | 1% of the total so far |
| Rate per unit | Total ÷ the quantity analysed, to the nearest ₹0.05 |
Items covered
| Item | CPWD DAR 2023 item | CPWD rate (Delhi, 2023) |
|---|---|---|
| Excavation in foundation trenches by machine | 2.8.1 | ₹260.30 per m³ |
| Filling excavated earth in trenches and plinth | 2.25 | ₹196.00 per m³ |
| PCC 1:4:8, 40 mm aggregate | 4.1.8 | ₹6,812.00 per m³ |
| PCC 1:2:4, 20 mm aggregate | 4.1.3 | ₹7,878.50 per m³ |
| RCC 1:1.5:3, foundation to plinth (concrete only) | 5.1.2 | ₹9,045.75 per m³ |
| TMT reinforcement Fe 500D | 5.22.6 | ₹107.85 per kg |
| Brickwork 1:6, foundation and plinth | 6.1.2 | ₹7,132.25 per m³ |
| Brickwork 1:6, above plinth (with lifting) | 6.4.2 | ₹9,105.95 per m³ |
| 12 mm cement plaster 1:6 | 13.4.2 | ₹343.65 per m² |
| 15 mm cement plaster 1:6 | 13.5.2 | ₹395.35 per m² |
| 6 mm cement plaster 1:3, ceilings | 13.16.1 | ₹300.45 per m² |
| Cement-based wall putty, 1 mm | 13.80 | ₹156.05 per m² |
| Acrylic emulsion paint, two coats | 13.82.2 | ₹137.45 per m² |
With “Match CPWD DAR” selected and the default rates, the calculator gives these same figures.
Worked example: PCC 1:4:8
For 1 m³ of PCC 1:4:8 with 40 mm aggregate, the CPWD analysis takes 0.65 m³ of 40 mm and 0.24 m³ of 20 mm aggregate, 0.47 m³ of coarse sand and 0.17 tonne of cement, with 0.10 day of mason, 1.63 days of beldar, 0.70 day of bhisti, and mixer and vibrator time. At CPWD’s 2023 Delhi rates these come to ₹4,788.29. Adding 1% water charges and 15% for profit and overheads gives ₹5,561.60 per m³; adding GST and cess as CPWD does gives ₹6,812.00.
Frequently asked questions
What is rate analysis in construction?
Rate analysis works out the cost of one unit of an item of work, such as 1 m³ of concrete or 1 m² of plaster, from the materials, labour and machinery it needs, plus water charges, overheads and profit. Contractors use it to price work and owners use it to check quotes.
Where do the quantities in this rate analysis come from?
The material, labour and machinery quantities are taken from the CPWD Delhi Analysis of Rates 2023, the analysis the Central Public Works Department uses for its schedule of rates. The default basic rates are the DAR’s Delhi rates of 2023; replace them with the rates in your city.
How much labour does 1 m³ of PCC 1:4:8 need?
In the CPWD Delhi Analysis of Rates 2023, 1 m³ of PCC 1:4:8 with 40 mm aggregate takes 0.10 day of mason, 1.63 days of beldar and 0.70 day of bhisti, with 0.17 tonne of cement, 0.47 m³ of coarse sand and 0.89 m³ of stone aggregate.
What overheads and profit are added in rate analysis?
The CPWD analysis adds 1% water charges, then GST through a multiplying factor, then 15% for contractor’s profit and overheads, and 1% labour cess. This calculator adds water charges and 15% profit and overheads by default, and lets you switch GST and cess on to match the CPWD figures.
Does the rate for RCC include steel and shuttering?
No. In the CPWD analysis, RCC is priced per m³ of concrete excluding reinforcement and centring and shuttering. Add the steel separately per kg, and shuttering per m² of contact area.
Why is my contractor’s rate different from this?
Local material and labour rates, the size of the job, access, transport distance and the contractor’s margin all change the rate. Enter your local basic rates to bring the analysis closer to your site.
More quantity tools
Brickwork BOQ calculator
Bricks, cement and sand for all the walls of a building.
PCC calculator
Volume and materials for the PCC under footings and floors.
Construction cost calculator
A rough budget for the whole house per sq ft.
All quantity tools
Earthwork, PCC, concrete, brick, steel, cement and plaster.
Source: Central Public Works Department, Delhi Analysis of Rates 2023, Volumes I and II. Speak Arch is not connected with CPWD.
Disclaimer: Online educational publication only. Not a quotation, tender rate or substitute for an estimate by a qualified engineer or quantity surveyor. Full disclaimer · contact@speakarch.com
Last updated: 10 November 2026